'The preliminary earthworks, which began in early September, are now well advanced. The entire construction project is well on schedule and we are more than satisfied with the progress made`, says Tino Schenk, Project & Sales Manager at OEST ENERGIES GmbH & Co. KG. The fuel tanks for HVO100, Diesel, Super E10, Super E5, Super Plus and the Ad-Blue tank have been installed in the ground and are now being connected to the necessary filling, suction and ventilation lines. Commissioning of the filling station is planned for June 2025.